pp. 4–5The payments for municipal services (PMS) program was established in 1973. Through this program, the state provides annual payments to reimburse municipalities for all or a portion of property tax supported expenses incurred in providing services to state facilities, which are exempt from property taxation. The intent of the program is to aid in the reduction of local property taxes by making an equitable contribution toward the cost of certain municipally provided services. In 2024-25, $18,584,200 will be paid by the state through the PMS program.
Payments are made for fire and police protection, extraordinary police services, garbage and trash collection and disposal, and other approved direct services. Municipal services such as water, sewer, and electrical power that are financed in whole, or in part, by special charges or user fees must be paid for by the state agency responsible for the facility receiving the services.
Current Program
The PMS program is administered according to program guidelines developed by the Department of Administration (DOA) and approved by the Joint Committee on Finance. The current guidelines are as follows:
- 1.Annual payments to towns, villages, and cities are determined largely by formula. Payment adjustments may be made as a result of negotiations between a municipality and DOA.
- 2.Formula payments are in recognition of fire and police protection and solid waste handling services provided by municipalities that impose no special charge or user fee for these services.
- 3.The formula attempts to approximate the local costs of eligible services that are attributable to the state facility and financed out of local property tax revenue. Due to various state and federal aid payments, less than 100% of police, fire, and solid waste handling expenditures are supported by the local property tax.
- 4.Prescribed reductions of payments are made where the state maintains self-provided police protection, reflecting state responsibility for institutional and building safety.
- 5.In the past, while the PMS formula had not generally applied, counties could receive PMS payments on claims for county law enforcement services that were provided when such services were specifically requested by a state facility administrator. However, the program guidelines have since been modified to eliminate program payments to counties. Rather, counties can indirectly receive reimbursement for eligible costs through an intergovernmental agreement with the municipality in which the state facility receiving the county services is located. Any payment made to the county by the municipality for those services can then be submitted as an eligible cost to be included with the costs used to determine that municipality's formula payment.
- 6.If an overpayment or underpayment in excess of $5,000 during one program year is made to a municipality due to incorrect fiscal data, a building inventory misallocation, or an inadvertent oversight and is discovered within two years of the PMS payment being sent to the municipality, an adjustment to that payment will be made in subsequent PMS payment years.
p. 6Applying these guidelines results in an esti- Table 1: Sample Calculation of PMS Entitlement mate of the municipal cost of providing the three
Step I: Determine Net Cost of Providing Service
services to state-owned property, referred to as the
| PMS entitlement. Entitlements are calculated on | A. Gross Service Costs | $2,480,000 (A) |
| [Personnel, fringe benefits, | ||
| the basis of previous calendar year fiscal infor- | equipment, capital development, etc.] | |
| mation. For example, entitlements calculated for | B. Direct Service Revenues | 280,000 (B) |
| services provided in 2024 are based on 2023 costs, | [Specific state aid, specific federal | |
| revenues, and property values. The actual pay- | aid, subsidies, service fees, etc.] | |
| C. Net Service Costs [(A)-(B)] | 2,200,000 (C) | |
ments will be made to municipalities in 2025.
Step II: Determine Portion of Net Cost Supported By Local
Property Tax
[Assumes that unrestricted state aid payments are used locally to help
| Formula Calculation | defray part of the net cost.] |
| D. Municipal Property Tax Levy $7,480,000 (D) | |
| E. Sum of General Aids 7,920,000 (E) | |
| The following description of the PMS formula | [State county and municipal aids, |
| is presented to assist in understanding the sample | utility aid, and expenditure restraint] |
| calculation presented in Table 1. The first step | F. Total General Revenue [(D)+(E)] 15,400,000 (F) |
| G. Percentage of General Revenue Provided .485714 (G) | |
| (Step I) in this formula involves calculating the net | By the Tax Levy [(D)÷(F)] |
| costs incurred by the municipality in providing | H. Net Cost Supported by Local Property 1,068,571 (H) |
| each eligible service on a municipality-wide basis. | Tax [(C)x(G)] |
| The net costs are determined by subtracting mu- | Step III: Determine Portion of Net Cost That is Attributable |
| nicipal revenues that are directly related to a par- | to State Facilities |
| ticular service (service charges, specific state or | I. Value of State-Owned Property $32,900,000 (I) |
| federal aid payments, and intergovernmental sub- | (Net of land) |
| sidies) from the gross costs of providing the ser- | J. Value of Locally-Owned, Taxable 616,200,000 (J) |
| vice. | Property (Net of land) |
| K. Total Value of Improvements to 649,100,000 (K) | |
| Property [(I)+(J)] | |
| The second step (Step II) in the formula in- | L. Proportion of Total Value Which .05069 (L) |
| volves calculating the amount of property taxes | is State-Owned [(I)÷(K)] |
| used to finance the net cost of each service. The | M. PMS Entitlement [(H)x(L)] 54,165 (M) |
municipality's property tax levy for municipal purposes is divided by the sum of the municipality's
the total value of real estate improvements within
property tax levy for municipal purposes and state
the municipality. This is repeated for each of the
unrestricted aid payments (this sum equals total
three eligible costs (fire and police protection and
general revenue). This ratio, which represents the
solid waste handling services) and the three
proportion of the municipality's general revenues
amounts are totaled to yield the municipality's
provided through the property tax, is multiplied by
PMS formula entitlement. Municipalities with an
the net cost of each service to yield the cost fi-
entitlement amount of less than $100 do not re-
nanced through the municipal property tax.
ceive a payment.
The final step (Step III) in the formula involves
| allocating a portion of the tax cost of each service | Additional negotiation between DOA and mu- |
| to the state-owned facilities within the municipal- | nicipalities on factors related to the state providing |
| ity. The tax cost of each service is multiplied by | its own services or a municipality providing |
| the ratio of the value of state-owned facilities to | specific services may change the results of the |
p. 7basic formula calculation.
Prior to 2013 Wisconsin Act 20, annual PMS payments could not be made until the Joint Committee on Finance reviewed and approved the results of the formula calculations. Act 20 removed the Committee's role in approving the annual payment distribution, but retained the Committee's role in approving any changes to the program guidelines.
Historically, PMS payments were made out of the state's general fund, through a general purpose revenue (GPR) appropriation. Under 2023 Act 12, beginning in 2024, PMS payments are made from the local government fund, which is funded from an annual transfer from the general fund.
If the PMS appropriation is not sufficient to fund total entitlements, payments are prorated. If the appropriation exceeds total entitlements, the excess would lapse to the local government fund.
Level of Funding
The relation between PMS entitlements and appropriations since the program's inception can be categorized by time period. Entitlements exceeded appropriations from 1973 to 1977, with proration ranging from 67.2% to 89.0%. Appropriations exceeded entitlements from 1978 to 1982, allowing payments at 100% of entitlements. Since 1982, entitlements have again exceeded appropriations and payments have again been prorated.
Declining entitlement amounts in some years could have been due to several factors, including lower total costs of services provided to state facilities, sales of state facilities, or other real estate values outpacing the value of state facilities within eligible municipalities. In other years, just the opposite occurred as entitlements increased significantly due to increases in police and fire service costs and increases in the value of state facilities that outpaced increases in private real estate values, particularly due to the construction of additional state facilities in the City of Madison.
Table 2 shows PMS payments and entitlements from 2015 through 2024. Statewide entitlements grew by 8.9% over the 10-year period. Over the same period, the funding level for the program has remained at a constant level of $18.6 million annually. Together, these two factors have resulted in a decline in the percentage of statewide entitlements covered by the PMS appropriation.
Table 2: Statewide PMS Entitlements and Payments
| Statewide Change in | Statewide | Percent of | |
|---|---|---|---|
| Year Entitlement Entitlements | Payment | Entitlements | |
| Percent | Payments as | ||
| 2015 $45,371,602 | $18,584,200 | 41.0% | |
| 2016 48,975,279 | 7.9% | 18,584,200 | 37.9 |
| 2017 48,650,175 | -0.7 | 18,584,200 | 38.2 |
| 2018 47,777,335 | -1.8 | 18,584,200 | 38.9 |
| 2019 53,625,738 | 12.2 | 18,584,200 | 34.6 |
| 2020 53,703,005 | 0.1 | 18,584,200 | 34.6 |
| 2021 48,291,564 | -10.1 | 18,584,200 | 38.5 |
| 2022 48,749,028 | 0.9 | 18,584,200 | 38.1 |
| 2023 48,680,769 | -0.1 | 18,584,200 | 38.2 |
| 2024 49,402,860 | 1.5 | 18,584,200 | 37.6 |
For 2024, the PMS appropriation covered 37.62% of the $49.4 million in entitlements. PMS payments were approved for 361 municipalities in that year. Payments ranged from $38 to the Town of Lake in Price County, which had $101 in entitlements, to $8.1 million to the City of Madison on $21.4 million in entitlements.
The 1987-89 budget established a procedure for program revenue (PR), program revenue-service (PR-S), and segregated revenue (SEG) appropriations to be charged for municipal services to facilities funded through these appropriations. Until 2024, these annual payments to municipalities were made directly from the p. 8state's general fund through a GPR appropriation. Beginning in 2024, these municipal payments are made from a SEG appropriation from the local government fund, which is funded through an annual transfer from the state's general fund. However, after payments are made, DOA transfers amounts associated with PR, PR-S, and SEG appropriations that fund state facilities back to the state's general fund as GPR-Earned.
Table 3 shows the 2023-24 chargeback amounts by agency. The largest chargeback was incurred by the University of Wisconsin System (73.0% of the total). This figure would be larger, but PR appropriations associated with academic student fees are exempt from the chargeback. In total, 2023-24 chargebacks equaled 47.6% of the PMS appropriation for that year.
The major issue related to the PMS program has been whether it should be funded at 100% of entitlements. Some local officials have argued that proration of entitlements results in municipalities not being fully compensated for the services they provide to state facilities. Consequently, the cost of providing municipal services is shifted from the state-owned exempt property to owners of taxable property.
However, it has also been argued that factors, in addition to PMS, tend to offset the local costs associated with tax exempt state facilities. Although no specific data are available to indicate the precise economic benefit to municipalities of having state facilities, direct public investment, public payrolls, and the multiplier effect on local private investment and payrolls are of some value. The location of state facilities may also result in lower-than-average unemployment rates for the corresponding municipalities
Table 3: 2023-24 GPR-Earned Amounts from Chargebacks for PMS
| Agency | Amount |
|---|---|
| Administration | $1,031,068 |
| Agriculture, Trade, and Consumer Protection | 1,391 |
| Corrections | 26,346 |
| Educational Communications Board | 5,319 |
| Health Services | 366,275 |
| Historical Society | 53,535 |
| Kickapoo Reserve Management Board | 1,035 |
| Natural Resources | 220,722 |
| Public Instruction | 39,479 |
| State Fair Park Board | 263,845 |
| Transportation | 294,229 |
| University of Wisconsin System | 6,464,964 |
| Veterans Affairs | 80,530 |
| Workforce Development | 3,160 |
| Total | $8,851,898 |